Guides / Daily construction report template (free Excel, with punch list)

Daily construction report template (free Excel, with punch list)

By Emre, Pulad Labs · Updated 2026-11-18

A free daily construction report and punch list template in Excel. Fill it on site, print or save it as PDF, sign it and send it to the GC or client. No sign-up.

Download the template (Excel, free) Versión en español

What is in the file

What to write in a daily report

A daily report (also called a daily log or site diary) is your record of what happened on site that day. Owners, GCs, insurers and courts rely on it when there is a dispute about delays, extra work or an accident, so the details that matter most are the ones people skip:

  1. Who was on site: each trade and company, number of workers and hours. This supports your pay application and any time-and-materials claim.
  2. Weather, twice a day: rain, wind and temperature explain lost days and concrete or roofing decisions.
  3. Delays with their cause: late delivery, waiting on another trade, an owner change, an inspection. Write the cause the same day; it is what protects you in a delay claim.
  4. Instructions and changes: who asked for what and when, even verbally. Many change-order disputes are decided by a dated note.
  5. Inspections and tests: inspector name, result, what must be corrected.
  6. Safety: incidents, near misses and the toolbox talk topic.
  7. Photos: dated photos of progress and of any problem, referenced by number.

Punch list tips

Walk the job room by room, give each item a number, a photo and a responsible trade, and set a due date. Close items only after you have seen the fix; write the date and who closed it. Send the open items to each trade the same day.

Want this as a phone app?

General information, not legal or contract advice. Your contract, your GC or the project owner may require a specific form; use theirs when they do.

Frequently asked questions

Is the template free?

Yes. Download it, change it and share it. No sign-up.

Does it work in Google Sheets?

Yes. Upload it to Google Drive and open it with Google Sheets; the formulas and the status colours work there too.

What is the difference between a daily report and a site diary?

They are the same record. In the US it is usually called a daily report or daily log; in the UK and Australia a site diary.

How long should I keep daily reports?

At least until the warranty and claim periods of the project end; many contractors keep them for six years or more. Check your contract.