Guides / SWPPP inspection report template
SWPPP inspection report template
Copy this report into Word or Google Docs, or print it for the truck. Fill one per inspection, attach photos, and keep it with the SWPPP.
Free stormwater site inspection report
STORMWATER (SWPPP) SITE INSPECTION REPORT Project / site: [name, address] Permit / NOI tracking no.: [ ] Operator(s): [ ] Inspector: [name, qualifications] Date: [ ] Time: [ ] Inspection type: [ ] routine (every 7 / 14 days) [ ] within 24 h of 0.25 in storm [ ] final / other Rain since last inspection: [__] in Date of storm: [ ] Discharge at outfalls during inspection: [ ] yes [ ] no Weather now: [ ] Site status: [ ] active [ ] temporarily stabilized [ ] frozen / winter conditions AREAS INSPECTED: [ ] cleared/graded areas [ ] stockpiles [ ] outfalls / discharge points [ ] stormwater controls [ ] construction entrance [ ] material storage [ ] concrete washout [ ] dewatering CONTROLS (BMPs) BMP / location | Installed per plan? | Working? | Maintenance needed | Corrective action / due date Silt fence [ ] | [ ] yes [ ] no | [ ] | [ ] | [ ] Inlet protection [ ] | [ ] | [ ] | [ ] | [ ] Stabilized construction entrance / track-out [ ] | [ ] | [ ] | [ ] | [ ] Sediment basin / trap [ ] | [ ] | [ ] | [ ] | [ ] Stabilization (seed, mulch, blanket) [ ] | [ ] | [ ] | [ ] | [ ] Concrete washout [ ] | [ ] | [ ] | [ ] | [ ] Waste / material storage, spill kit [ ] | [ ] | [ ] | [ ] | [ ] Sediment or pollutants leaving the site / visible in discharge: [ ] no [ ] yes, describe: [ ] Photos taken: [ ] yes Number: [ ] CORRECTIVE ACTIONS FROM PREVIOUS INSPECTION Item | Date found | Date completed | Notes [ ] | [ ] | [ ] | [ ] CERTIFICATION I certify under penalty of law that this report and all attachments were prepared under my direction or supervision. [Use the exact certification wording required by your permit.] Inspector signature: ____________________ Date: ______ Operator / authorized signer: ____________________ Date: ______
General information, not legal or permit advice. Inspection frequency, forms and certification wording come from your Construction General Permit (EPA or state); use the version that covers your site.
Want SWPPP inspections on your phone, with a rain alert when a 24-hour inspection is due?
Frequently asked questions
How often do SWPPP inspections have to be done?
Under EPA's Construction General Permit, sites are generally inspected at least once every 7 calendar days, or once every 14 days plus within 24 hours of a storm of 0.25 inches or more. State permits differ; follow the one that covers your site.
What goes in a stormwater inspection report?
Inspection date and type, inspector, rainfall since the last inspection, any discharges, the condition of every control (BMP), problems found, corrective actions and dates, photos and the signed certification.
How long must inspection reports be kept?
Keep them with the SWPPP on site during construction and for the period your permit requires after the site is stabilized, often three years.